The installation of the pig manure organic fertilizer equipment dryer should strictly follow the requirements of the assembly drawing and foundation drawing for standardized construction. Before installing the pig manure organic fertilizer equipment dryer, its components and auxiliary parts should be thoroughly inspected, wiped, cleaned, and complete. Due to the fact that the organic fertilizer equipment dryer is a long and large equipment, the installation should be carried out in this order and method. Below, editor will explain the installation sequence of the pig manure organic fertilizer equipment dryer:
1. Drawing the foundation line: Correctly mark the cross line, elevation line, and center marking plate on the foundation marking plate to achieve ease of use, accuracy, and consideration of not being covered after the installation of the machine base.
2. Installation of base and tugboat: Flatten the position of the shim, mark the center line of the base and tugboat, find the installation position of the base and tugboat according to the drawing requirements, level and align them, first grout the foundation hole, when the concrete reaches a certain strength, tighten the anchor bolts, recheck and pass, and then install the sand dryer cylinder.
3. Installation of cylinder and rolling ring: First, install the rolling ring on the cylinder. The concave joints required for fixing should be arranged in a staggered manner, with one in front and one in reverse. Adjust the thickness of the shim to maintain the corresponding gap between the rolling ring and the concave joint. Do not make them consistent, and spot weld the head of the concave joint bolt to the cylinder.
4. Installation of large gear: Before installation, check that there are no collision marks on the mating surface interface. Clean the contact surface between the large gear and the cylinder, carefully align the two halves of the gear and tighten the interface bolts, and then install the large gear on the cylinder. Rotate the cylinder and check the radial runout and lateral swing of the large gear until the calibration is qualified.
5. Install small gears, reducers, and motors: Adjust the meshing parameters of the large and small gears according to the installed large gears and meet the equipment requirements. Fix the position of the small gears, reducers, and motors.
6. Install gear cover: Make it evenly spaced from the edge of the gear.
Taian Hongxin Environmental Protection Technology reminds everyone that after all the above work is completed, secondary grouting should be carried out, and the requirements for grouting should be in accordance with the relevant regulations of civil engineering design. The installation review and debugging work related to grouting shall be carried out simultaneously to ensure the installation quality of the pig manure organic fertilizer equipment dryer.